Ministry of Environment, Spatial Planning and Public Works-General Secretariat of Public Works-Special Public Authority for Concession Projects
Revision and Upgrade of traffic and revenue forecasts of Thessaloniki Submerged Tunnel
Year: 2006
Brief Description:
ΤRIAS SA undertook this project that lasted three months and had the following basic activities:
Restructuring and rerunning traffic simulation models that were developed in the previous study of traffic forecasts for the Tunnel in 2003, in order to be realigned to changes incorporated in Tender Documents
Reliability check of the new models
Model runs in order to estimate traffic demand. Models will be run for different time horizons and different pricing scenario
Traffic and Revenue forecast projection in a six-month basis during the operation period of the project